Exit 67 Sanitary Sewer Extension

The Town of Vernon has been awarded a $1,636,696 grant through the State Bond Commission, which is administered by the Connecticut Department of Energy & Environmental Protection. The grant will be used for the Town of Vernon’s Water Pollution Control, which conducted a review of the town’s wastewater collection and treatment facilities. The town has retained Tighe & Bond, Inc. as the engineer to design new sanitary sewer lines and a pump station. The new utilities will serve several undeveloped parcels of industrial, commercial and residential land in the area of Exit 67 off I-84 in Vernon. Additionally, address the failing septic systems in the area.

The project includes the installation of approximately 5,600 feet of 8-inch gravity sewer main, approximately 1,200 feet of 6-inch sewer laterals, approximately 2,100 feet of 6-inch sewer force main, and one new pump station. The gravity sewer main, low-pressure sewer main, and pump station would maintained by Vernon’s Water Pollution Control Authority. The new gravity sewer will connect to the new pumping station, and the new sewer force main will connect to an existing 18-inch gravity sewer main. 

Below find documents and links for project details, updates, and meeting details pertaining to the project.

Questions about the lateral placement for residents can be directed to Kelly Morris at Tighe & Bond,For additional questions please contact the Vernon WPCA Office at 860-870-3699. 

Task Name

Duration

Start

Finish

Submittals and Lead Times

252 days

Wed 4/24/24

Thu 4/10/25

Sewer Main

91 days

Thu 7/18/24

Mon 12/16/24

Exit 67 Sewer Schedule

113 days

Thu 7/18/24

Mon 11/21/24

8" Gravity Sewer Main

17 days

Thu 7/18/24

Tue 8/9/24

South Grove St

10 days

Wed 8/12/24

Tue 8/23/24

Sunrise Drive

10 days

Wed 8/26/24

Mon 8/29/24

Green Road

4 days

Wed 8/26/24

Mon 8/29/24

Reservoir Road

60 days

Tue 8/30/24

Mon 11/21/24

6" Force Sewer Main

30 days

Tue 10/11/24

Mon 11/21/24

Temporary Paving

90 days

Thu 7/18/24

Wed 11/20/24

Pump Station

171 days

Mon 9/2/24

TBD

Final Paving

15 days

Mon 4/21/25

Fri 5/9/25