ROADWAY and BRIDGE PROJECT UPDATES (Rev'd July 2008)

2005 Road Bond Program
Construction Schedule 2008 - 2011 (pdf)

* * *
Vernon Avenue Bridge over Hockanum River (pdf)

Vernon Roadway & Bridge Projects

High Street Reconstruction
Work has commenced on High Street and is scheduled to be completed in the fall of 2008.  Work shall include resetting the existing granite curbing, installing new drainage, sidewalks, and pavement.  The Connecticut Water Company is in the final stages of replacing the water main in this location.  AT&T shall be moving utility poles in conjunction with this project.  Detour will be by way of Vernon Avenue, Brooklyn Street and Court Street.  Please observe the temporary “No Parking” signs, which will be installed only around the immediate work area, and shall move as construction progresses.

Vernon Avenue - South Street to Rte. 30
Work has commenced on this project and will be completed by mid to late Summer ‘08.  The Detour will be by way of South Street and Rte. 30
           
Vernon Avenue Bridge over Hockanum River
Construction will begin on the deck replacement in Spring ’08.  Work is anticipated to be completed by the Fall ’08.  Detour will be by way of Brooklyn St., Court St., East Main St. and West Main St.

Center Road
Construction will resume early in Spring ’08. The work area will be from Peterson Rd. to Rte 83. Construction is anticipated to be completed by the end of the year ’08. The detour will be by way of Regan Rd., West St. and Rte. 30.
March 31 through April 29 Center Road from Bette Circle to Jonathan Drive
Install granite curb
Excavate grade
Pour sidewalks
April 14 through April 30 Peterson Road
Pour sidewalks
April 21 through May 9 Center Road Station 217+00 to Regan Road
Drainage work
May 6 through May 30 Excavate Center Road and Regan Road
June 2 through June 5 Pave Center Road and Regan Road
June 6 through July 30 Center Road
Install curb
Excavate sidewalk
Pour concrete
Aug. 15 through Sept. 30 Center Road
Loam and seed
Final Cleanup

Bolton Road - Indian Trail to Bolton Town Line
The Vernon Dept. of Public Works will begin construction on this project in Spring ’08.  The entire project will take two construction seasons.  The detour will be by way of Rte. 44, Cider Mill Rd, Lake St., Tunnel Rd. and South Frontage Rd.

 

Journal Inquirer

Area state legislative and town referendum results ... at 5:30 a.m.
By Journal Inquirer Staff
11/02/2004

Vernon: Three bonding referendum proposals were approved: for roads, water treatment, and sewers. The other four proposals were defeated.

At the referendum, voters approved $21.6 million for road, bridge, and sidewalk reconstruction, improvements to the town's wastewater treatment facility to reduce nitrogen discharge, and money to replace broken sewer pipes and renovate the Dart Hill Road pump station.

Taxpayers rejected spending $16 million to improve public buildings, clean and dredge the Tankerhoosen Lake, buy open space, and install a new town-wide telecommunications system.

Voters at a referendum Nov. 2 rejected a $37.6 million public improvement bond package that would have gone to town projects.

 

Home | About Vernon | Residents | Businesses | Points of Interest | Employee Directory | Contact Us | Bill Pay | Youth Sports
Services | Mayor | Town Council | Board of Education | Boards & Commissions | Legislators | Elections Administrator | Judge of Probate | Departments | Agendas/Minutes | Budgets


Copyright © 2008 Town of Vernon Connecticut. All rights reserved.
Powered by ImageWorks, LLC